PROJECT TIMELINE
Indicative construction timeline:
Site establishment:
​
Preparing the site to begin construction by installing signs, safety inductions, and OHS Plan documented and available on site.

Military Road hoarding installation:
​
Hoarding will be installed around the site along Military Road.

Military Road footpath works:
​
Footpath works along Military Road will include repaving the existing footpath.
​

Supermarket opening date:
​
Official store opening is planned for mid-2023.

August 2022
October 2022
Commencing - mid May 2023
Late August 2023
Community engagement will take place throughout the construction program.
​